Project

Others Construction

Modern Harmony House is a residential retreat designed to blend with its natural surroundings. The project was guided by minimalist design principles and sustainable material choices.

Vientiane capital in Laos PDR

Waste Water Treatment Plant & Electical Installation

It is a waste water treatment and electrical installation works for garment factory at Saysettha Development Zone (SDZ). 

Lao PDR

Dam Spillway Upgrade and Sediment Removal, Phonsavanh– Phu Bia Mining

Phu Bia built the sediment control dam in order to minimize the impact to rice fields and gardens downstream of Houay Naking as temporary structure in 2013 and after the KTL prospect couldn’t develop due to the global copper price therefore the dam to be upgrade for permanent performance life. The project has two main tasks; first is removal the sediment from the dam basin and upgrade the spillway to be reinforced concrete structure (existing is gabion).